State Road Development Corporation · Pre-Tender Audit ₹18.4 Cr Discrepancies Caught

Pre-Tender DPR Validation, Schedule of Rates (SOR) Audit & FIRR Verification

A State Road Development Corporation audited a 1,200-page consultant DPR package across 380 km of highway widening using Aagento AI DPR Validation, detecting ₹18.4 Cr in arithmetic quantity mismatches and outdated SOR rates in 48 hours.

48 Hours
Audit Speed
Completed in 2 days vs. 4 weeks manual
₹18.4 Cr
Discrepancies Caught
Arithmetic & unit rate escalation errors
1,200 Pgs
DPR Dossier Scrutinized
Cross-referenced against typical cross-sections
100%
Proforma 2023 Compliant
Approved for Central Government grants
AI DPR VALIDATION // 1,200 PGS CROSS-REFERENCED
Aagento Generative Engine
01 // CONTEXT

Pre-Tender Governance Mandate

Before floating an EPC tender for a 380 km State Highway rehabilitation and widening project, the government corporation needed an exhaustive independent engineer (IE) audit of the consultant-submitted Detailed Project Report (DPR).

02 // CHALLENGE

The Risk of Unchecked Errors

The DPR spanned 1,200 pages across 4 volumes. Manual review typically takes 4 weeks and frequently overlooks cross-table discrepancies between drawing dimensions, Bill of Quantities (BOQ) sums, and current State PWD Schedule of Rates (SOR). Uncorrected errors lead to post-award claims and budget overruns.

Traditional Manual Baseline

4 Weeks Manual IE Audit · Overlooked SOR Inconsistencies · Post-Tender Claim Risks · Unverified IRR Models

Aagento AI Generative Result

48 Hours Audit · ₹18.4 Cr Arithmetic & Rate Mismatches Detected · 100% Proforma 2023 · Actionable Audit Report

03 // ARCHITECTURE

Aagento Generative AI Solution Pipeline

The project replaced fragmented human drafting with Aagento’s four-stage deterministic engineering pipeline:

Phase 1: OCR & Cross-Referencing
Quantity Takeoff Validation

Cross-referenced typical cross-section (TCS) pavement layers against the BOQ line items, flagging under-reported bitumen quantities.

Phase 2: SOR Database Matching
Rate Analysis Verification

Automated fuzzy lookup against the latest 2025–26 State PWD SOR, identifying 47 line items calculated with superseded unit rates.

Phase 3: Financial Model Scrutiny
FIRR & EIRR Recalculation

Re-ran discounted cash flow and sensitivity simulations for traffic growth rates under MoRTH Vol. 1 Proforma 2023.

Phase 4: Red-Flag Audit Report
Actionable Executive Summary

Synthesized an itemized 14-page compliance report with exact page citations and corrective recommendations.

04 // OPTIMIZATION

Semantic SOR Rate Verification

Aagento’s automated semantic matcher cross-referenced all 340 schedule items against the state government’s latest Schedule of Rates. The software uncovered 47 instances where outdated rates had been copied from previous year schedules, inflating estimated project contingency buffers.

05 // OUTCOMES

Tender Protection & Financial Integrity

Within 48 hours of ingestion, Aagento flagged ₹18.4 Crore in arithmetic discrepancies, duplicate earthwork entries, and outdated asphalt indexation. The consultant revised the tender schedules before tender notification, eliminating legal liability and contractor arbitration disputes during project execution.

Standard Engineering Deliverables Generated
Itemized 14-Page Red-Flag Audit ReportCorrected BOQ Schedule in ExcelFIRR & EIRR Sensitivity MatrixProforma 2023 Verification CertificateCross-Section Quantity Takeoff Verification
"Aagento’s audit caught ₹18.4 Cr in errors that our manual review completely missed. It paid for itself a hundred times over before we even issued the tender."
— Managing Director, State Road Development Corporation
Accelerate Your Infrastructure Pipeline

Ready to Achieve Similar Results on Your Next Corridor?

Whether you are preparing a multi-kilometer highway DPR, rushing bridge GAD approvals for freight corridors, or digitizing legacy infrastructure into BIM, our engineering team is ready to walk you through our platform.

Talk to Engineering Team